Quang Nam strives to disburse more than 90% of capital plan for transport projects

Việt NamViệt Nam21/01/2025


z6250144513228_b9ea51422a0e96480e5b6392d8eb311d.jpg
The implementation volume of Van Ly bridge project (Van Ly bridge and access road project) is high. Photo: CT

Accordingly, in 2024, the Traffic Department was assigned a plan to implement 23 projects, with a total capital plan of more than 1,679.4 billion VND. Of which, central capital accounts for more than 605.6 billion VND; foreign capital is more than 531.2 billion VND and provincial budget capital is more than 542.9 billion VND.

Mr. Nguyen Van Thuong - Director of the Traffic Department said that the total disbursement value as of January 17, 2025 is 1,426.7/1,679.3 billion VND, reaching 85% of the assigned plan. It is expected that by January 25, the unit will strive for the total disbursement value to reach more than 90%; the provincial budget capital alone will reach 100%.

The leader of the Traffic Department added that in early January, the unit disbursed the capital plan for 2025 for a number of projects that still owed the implementation volume of 2024. Typically, the Van Ly bridge project and access road, Tam Hoa main road, and Nghia Tu bridge.



Source: https://baoquangnam.vn/quang-nam-phan-dau-giai-ngan-dat-hon-90-ke-hoach-von-cac-du-an-giao-thong-3147970.html

Comment (0)

No data
No data

Same tag

Same category

Fireworks explode, tourism accelerates, Da Nang scores in summer 2025
Experience night squid fishing and starfish watching in Phu Quoc pearl island
Discover the process of making the most expensive lotus tea in Hanoi
Admire the unique pagoda made from more than 30 tons of ceramic pieces in Ho Chi Minh City

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product