Determined to complete the target of 3,000 km of expressway by the end of 2025

On the morning of July 31, Prime Minister Pham Minh Chinh, Head of the State Steering Committee for important national projects and works, key to the transport sector, chaired an online conference to review the work of the Steering Committee in the first 6 months of 2025 and the peak emulation period of "500 days and nights of emulation to complete 3,000 km of expressway".

Báo Đắk LắkBáo Đắk Lắk31/07/2025

Attending at the Dak Lak Provincial People's Committee bridge were Vice Chairman of the Provincial People's Committee Truong Cong Thai; representatives of relevant departments, branches and localities.

The meeting was also connected online to communes and wards of the province where the project passes through.

Prime Minister Pham Minh Chinh delivered a concluding speech at the conference.
Prime Minister Pham Minh Chinh delivered a concluding speech at the conference.

According to the report of the Ministry of Construction , in the first 6 months of 2025, investment procedures were completed to start construction of 5 expressway projects with a total length of 271 km and procedures are continuing to be implemented for 3 projects, with a total length of 302 km, expected to start construction on August 19, 2025.

Regarding site clearance, up to now, projects scheduled to be completed in 2025 have been basically completed, with only a few additional access roads or high-voltage power lines remaining. It is expected that by August 19, 2025, an additional 208 km of expressways will be completed, bringing the total number of expressways nationwide to 2,476 km.

Delegates attending the conference at the Dak Lak Provincial People's Committee bridge.
Delegates attending the conference at the Dak Lak Provincial People's Committee bridge.

Expressway projects scheduled for completion in 2025 to reach the target of 3,000 km have accelerated to increase production. Many projects scheduled for completion in 2026 have also made efforts to implement, striving to shorten the schedule by 4-5 months.

Regarding emulation and reward work, after the Prime Minister launched the peak period of "500 days and nights of emulation to complete 3,000 km of expressway", ministries, branches and localities have actively responded and participated, achieving many remarkable results. The Ministry of Construction has awarded 15 groups and 33 individuals; has submitted to the Prime Minister for awards to 14 groups and individuals with outstanding achievements in emulation movements.

Contractor representatives expressed their opinions at the conference.
Contractor representatives expressed their opinions at the conference.

Speaking at the conference, the Prime Minister emphasized that this time marks exactly one month since the whole country has been operating the two-tier local government model; although facing many difficulties and challenges, overall, the local government has initially operated stably, smoothly and promptly. In the spirit of continuing to race against time, only discussing work, not retreating, with the highest responsibility, the Government and ministries, branches and localities must resolutely complete the goal of having at least 3,000 km of expressway by the end of 2025 set by the 13th Party Congress.

According to the Prime Minister, there are only 5 months left, while the workload is still very large. To complete the tasks of 2025, all levels and sectors from the central to local levels must continue to be highly determined, make great efforts, and take drastic actions to complete the set goals.

The conference is connected online with communes and wards where the project passes.
The conference is connected online with communes and wards where the project passes.

The Prime Minister requested that competent authorities closely follow the implementation progress, continue to direct investors and contractors to organize construction in 3 shifts and 4 teams, proactively remove difficulties, apply technical solutions to shorten construction time, and ensure completion of projects in 2025.

Ministries and sectors review legal regulations to continue to propose amendments and supplements in the direction of promoting decentralization, delegation of power, enhancing the responsibility of localities and grassroots levels along with inspection and supervision; shortening the time to implement procedures... Localities continue to perfect the organizational apparatus, absolutely not allowing interruptions in site clearance and construction organization of projects when merging provinces as well as organizing two-level governments.

Source: https://baodaklak.vn/kinh-te/202507/dut-khoat-hoan-thanh-muc-tieu-3000-km-cao-toc-vao-cuoi-nam-2025-74205fe/


Comment (0)

No data
No data
Wild beauty on Ha Lang grass hill - Cao Bang
Missiles and combat vehicles 'Made in Vietnam' show off their power at A80 joint training session
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy

Heritage

Figure

Business

No videos available

News

Political System

Destination

Product