Permanent Vice Chairman of the Provincial People's Committee Nguyen Van Thi and members of the working delegation inspected and surveyed the actual progress of project implementation.
Accompanying him were comrade Nguyen Tien Hieu, member of the Provincial Party Standing Committee, Head of the Management Board of Nghi Son Economic Zone and provincial industrial parks; member of Working Group No. 2; representatives of leaders of provincial departments, branches and Nghi Son town.
Permanent Vice Chairman of the Provincial People's Committee Nguyen Van Thi and members of the working delegation inspected and surveyed the actual progress of project implementation.
Before working with key officials of Nghi Son town, Nghi Son Economic Zone Management Board and industrial parks of the province, Standing Vice Chairman of the Provincial People's Committee Nguyen Van Thi and members of the working delegation inspected and surveyed the actual progress of the North-South Expressway connecting project, National Highway 1A to Nghi Son Port; Project for comprehensive development of dynamic urban areas - Tinh Gia urban sub-project, Thanh Hoa province.
According to the report, the Nghi Son Economic Zone Management Board and industrial parks are allocated a plan of VND 84,080 billion in 2025, of which the capital for 2024 is extended to VND 24,299 billion, the capital plan for 2025 is VND 59,781 billion, with a total of 13 projects.
Overview of the working session.
The Management Board of Nghi Son Economic Zone and Thanh Hoa Industrial Zones Construction Investment Projects has a planned capital of VND 619,708 billion in 2025, of which the capital for 2024 is extended to VND 21,261 billion, the capital plan for 2025 is VND 598,447 billion, with a total of 5 projects.
Nghi Son town's planned capital for 2025 is 883,751 billion VND, of which the capital for 2024 is extended to 259,862 billion VND, the capital plan for 2025 is 623,889 billion VND, with a total of 4 projects and 3 national target programs.
Delegates attending the meeting.
However, in the implementation, the disbursement progress has not been ensured: Nghi Son Economic Zone Management Board and industrial parks, the average disbursement rate is 33.7%, not meeting the disbursement progress according to the direction of the Provincial People's Committee Chairman in Directive No. 02/CT-UBND dated January 17, 2025 (2/13 projects ensure disbursement progress).
Delegates attending the meeting.
The Management Board of the Nghi Son Economic Zone and Thanh Hoa Industrial Zones Construction Investment Project, the average disbursement rate is 11%, not meeting the disbursement progress as directed by the Chairman of the Provincial People's Committee in Directive No. 02/CT-UBND dated January 17, 2025 (in particular, the Project to upgrade and repair the North-South Route 3 - Nghi Son Economic Zone, the disbursement rate is 100% as guaranteed according to the Directive).
Nghi Son town, the average disbursement rate is 6%, not meeting the disbursement progress as directed by the Chairman of the Provincial People's Committee in Directive No. 02/CT-UBND dated January 17, 2025 (in particular, the National Target Program for Socio-Economic Development in Ethnic Minority and Mountainous Areas, the National Target Program for New Rural Construction, the disbursement rates are 83% and 78% respectively, ensuring the disbursement value according to the Directive).
Delegates speaking at the meeting.
There are currently 5 projects facing difficulties and obstacles in site clearance and resettlement, including: Anti-erosion embankment and flood drainage dredging in Nghi Son Key Economic Zone (phase 1); East-West Road 4 - Nghi Son Economic Zone (phase 1); Expansion of resettlement area south of Ho Tung Mau Street, Bac Son Ward (Nghi Son Town); Integrated development project of dynamic urban areas - Tinh Gia Urban Sub-project, Thanh Hoa Province, WB loan; North-South Expressway connecting road, National Highway 1A to Nghi Son Port.
Speaking at the meeting, Comrade Nguyen Van Thi, Member of the Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Committee, Head of Working Group No. 2 acknowledged the efforts of Nghi Son town, Nghi Son Economic Zone Management Board and the province's industrial parks in the process of implementing the public investment plan in the past time. However, he frankly pointed out: The progress of disbursement of public investment capital in 2025 in Nghi Son town, Nghi Son Economic Zone Management Board and the province's industrial parks is still slow, especially in projects facing difficulties and problems in site clearance, resettlement, material prices, etc.
Permanent Vice Chairman of the Provincial People's Committee Nguyen Van Thi spoke at the meeting.
To promptly remove bottlenecks, the Standing Vice Chairman of the Provincial People's Committee requested departments and branches to continue to monitor, urge, and inspect the progress of implementation and disbursement of public investment capital and capital of the National Target Programs in 2025 of the projects; promptly synthesize and propose to competent authorities to remove difficulties and obstacles in the process of project implementation. At the same time, proactively review, report to the Provincial People's Committee for consideration, and submit to competent authorities to adjust and reduce the 2025 capital plan for slow-to-implement projects to transfer to fast-to-implement projects, in order to ensure the requirements on the progress of the disbursement plan.
For investors, based on the remaining project implementation volume, proactively develop detailed progress of each work item, and make detailed disbursement plans for each project managed by the unit or locality.
The Standing Vice Chairman of the Provincial People's Committee also requested the locality to urgently complete all tasks under its responsibility. At the same time, it is necessary to urgently resolve difficulties and obstacles in the compensation and site clearance work of the projects to promptly hand over the sites to investors to speed up the implementation progress, in order to ensure the disbursement of the 2025 capital plan in accordance with regulations.
Along with that, direct relevant units to inspect and review unfinished projects, promptly hand over records and documents to units selected by competent authorities to receive records and documents to continue implementing the project, ensuring that the project is not interrupted after the end of the district People's Committee's activities...
Quoc Huong