Speed ​​up construction of key transport projects

These days, the Ring Road 2 and Nguyen Trai Bridge project is entering an important construction phase. The investor and contractors are urgently speeding up the construction progress of the items.

Báo Hải PhòngBáo Hải Phòng15/09/2025

ring-2-1
The Ring Road 2 project, Tan Vu - Hung Dao - Bui Vien section, is one of the city's key projects, with a total investment of VND 7,020 billion. In 2025, the project was allocated capital of VND 3,218.5 billion.
belt 2
Due to the low and weak ground, the contractor must use the soil cement pile construction method. This method increases stability and reduces subsidence of the ground.
wheel-2-4
The section from the inter-ward road intersection to the end of the Hai Thanh overpass intersection has completed 331/520 bored piles; 15/42 piers.
wheel-2
Workers work hard on the construction site, ensuring the set progress.
wheel-2
The site clearance work has been paid attention to by localities where the project passes through, speeding up progress. In the photo: Construction of the Ring Road 2 project through Hung Dao ward.
ring - length 2
Bui Vien intersection has completed 62/98 bored piles, 3/8 pier bases, and 11/88 SPT girder slabs.
belt-2
Although the project is facing problems related to site clearance, contractors are trying to stick to the construction schedule.
the-prince-left-1
The Nguyen Trai Bridge construction investment project and urban beautification of the surrounding area, which started in December 2024, is a key traffic project of the city, with a total investment of 6,235.5 billion VND.

the-left-guy 2
Investors and contractors focus on close direction.
the-prince-left-3
Construction site on Thuy Nguyen ward side is bustling.
the-prince-left-4
The contractor is determined to carry out the construction of the bridge on Nguyen Trai Street safely and effectively.
the-prince-left-5
To ensure the progress of project construction, the City People's Committee requires localities to complete site clearance by October 2025.
LE DUNG

Source: https://baohaiphong.vn/tang-toc-thi-cong-cac-du-an-giao-thong-trong-diem-520870.html


Comment (0)

No data
No data

Same tag

Same category

Precariously swinging on the cliff, clinging to the rocks to scrape seaweed jam at Gia Lai beach
48 hours of cloud hunting, rice field watching, chicken eating in Y Ty
The secret of the Su-30MK2's top performance in the sky of Ba Dinh on September 2
Tuyen Quang lights up with giant Mid-Autumn lanterns during the festival night

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product