Vietnam.vn - Nền tảng quảng bá Việt Nam

Efforts to accelerate the construction progress of raising the clearance of Hong Ngu bridge in Dong Thap

Báo Giao thôngBáo Giao thông20/11/2024

Hong Ngu Bridge is being constructed the fastest among the bridges that are being raised in Dong Thap . It is expected that in December, the contractor will basically complete the onshore work.


3 continuous shifts

Mr. Vo Van Quang, Deputy Construction Manager, Bien Dong Construction and Consulting Joint Stock Company (construction contractor) said that the Hong Ngu bridge was started by the company at the end of May.

Nỗ lực GPMB, đẩy tiến độ thi công nâng tĩnh không cầu Hồng Ngự ở Đồng Tháp- Ảnh 1.

Contractors are busy raising the clearance of Hong Ngu bridge (Dong Thap).

Up to now, the project progress has reached more than 30%, the work on the An Loc ward side has been basically completed by the contractor and workers are being organized to construct on the An Thanh ward side.

Currently, at the construction site, the company has arranged for workers to do work related to bored piles and has completed 50/56 piles according to the new bridge structure specified in the construction plan.

"To raise the clearance of Hong Ngu bridge, the contractor must construct 8 pillars and 2 abutments. Currently, the contractor has basically completed 3 pillars and 1 abutment on the An Loc ward side," Mr. Quang added.

Nỗ lực GPMB, đẩy tiến độ thi công nâng tĩnh không cầu Hồng Ngự ở Đồng Tháp- Ảnh 2.

The contractor is striving to complete the onshore work by next December.

To complete the above mentioned volume of work, the contractor has increased 30% of human resources, equipment and machinery to the construction site.

At the same time, workers were organized to work in 3 continuous shifts, that is, working through the night to speed up construction progress.

"With the current way of organizing work, it is expected that by December, the contractor will complete 6 piers and 2 abutments on the shore.

After that, the contractor will organize workers to do the work under the river," said Mr. Quang.

Quickly remove land obstacles

Mr. Tran Van Tuan, the consulting and supervising unit, said that after the clearance was raised, the new Hong Ngu bridge has a horizontal clearance greater than 5.5m and is 2m higher than the old bridge.

Nỗ lực GPMB, đẩy tiến độ thi công nâng tĩnh không cầu Hồng Ngự ở Đồng Tháp- Ảnh 3.

Hong Ngu Bridge is still stuck with land acquisition, making it difficult for contractors to construct.

Up to this point, the contractor has basically completed the construction according to the set schedule.

With the current construction organization method, the workload at each time point will be guaranteed to be on schedule.

According to Mr. Vo Van Quang, the contractor is busy with construction, however, the current difficulty is that the land on both sides of Hong Ngu bridge is still stuck.

This issue needs to be resolved soon to facilitate the contractor's construction.

Accordingly, the total land area to be recovered for Hong Ngu bridge is 1,665 hectares.

The project has a total of 95 affected households and relevant units need to provide support and compensation in accordance with regulations.

Nỗ lực GPMB, đẩy tiến độ thi công nâng tĩnh không cầu Hồng Ngự ở Đồng Tháp- Ảnh 4.

Difficulties need to be resolved soon so that the Hong Ngu bridge clearance raising project can be completed on schedule.

Dong Thap Province Land Fund Development Center said that in December, relevant units will complete the approval of compensation plans for households affected by the construction of the Hong Ngu Bridge clearance elevation.

"After the compensation plan is approved, relevant units will urgently carry out the next documents and procedures to soon hand over the clean site to the construction unit to raise the clearance of Hong Ngu bridge," added a representative of the Land Fund Development Center of Dong Thap province.

Hong Ngu Bridge has a total land area to be recovered of 1,665 hectares, with a total number of households to be compensated of 95 households.



Source: https://www.baogiaothong.vn/no-luc-gpmb-day-tien-do-thi-cong-nang-tinh-khong-cau-hong-ngu-o-dong-thap-192241120181012624.htm

Comment (0)

No data
No data
Southeast Asian newspapers comment on the resounding victory of the Vietnamese women's team
Wild beauty on Ha Lang grass hill - Cao Bang
Vietnam Air Force practices preparing for A80
Missiles and combat vehicles 'Made in Vietnam' show off their power at A80 joint training session
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground

Heritage

Figure

Business

No videos available

News

Political System

Destination

Product