On this route, the bridge over the Vam Co Dong River was completed in early January 2025.
According to the Provincial Construction Investment Project Management Board, the DT822B project has a total length of 11.35km, invested in phase 1 according to grade IV road standards, 9m wide base, 7m road surface, and 30m planned site clearance. The total investment is over 918 billion VND; of which, the Central Government supports 300 billion VND, the rest comes from the provincial budget and other legally mobilized capital sources.
In 2025, the project was allocated capital of 210 billion VND, by mid-July, disbursement reached 94.53 billion VND, equivalent to 45.02%.
It is noted that the construction progress of the bid packages is being implemented simultaneously. Of which, the Vam Co Dong bridge, the largest item, constructed by the Hop Thanh - Bac Trung Nam Joint Venture since May 2023, has so far completed the bridge deck of 10/10 spans, completed the cantilever section, and is constructing the guardrail and sanding the bridgehead road. The implementation value reached 272.6/322.2 billion VND, equivalent to 84.58%.
The section from Vam Co Dong bridge to DT838 and Kenh 1 and Kenh 2 bridges was constructed by Quang Hung - Hai Duong Joint Venture, starting from January 2025. Up to now, the box culvert at Km9+417 has been completed, unsuitable soil has been excavated for 3,504/4,126m long, sand has been gathered to reach 49,600/98,000m³, bored pile construction has reached 3/6 Kenh 1 bridge piles and 1/8 Kenh 2 bridge piles. The implementation value has reached 25.5/124.99 billion VND, equivalent to 20.4%.
The section from DT825 to Ho Chi Minh road, constructed by Saigon Traffic Construction Joint Stock Company, started in February 2025, has excavated unsuitable soil for 2,439/2,800m long, the implementation value reached 0.95/49.57 billion VND (1.92%).
The section from Ho Chi Minh road to Vam Co Dong bridge, constructed by T&T Company, started in February 2025, has so far completed excavation of unsuitable soil for 3,250/3,636m long, with an implementation value of 2.37/58.65 billion VND (4.13%).
The site clearance work of the DT822B project has made progress but is still stuck. The plan has been approved and compensation payments completed for 286 households and 7 organizations, but there are still 3 households left.
The DT822B project is expected to complete the strategic transport infrastructure in the border area, effectively connecting with Ho Chi Minh Road, facilitating the circulation of goods and socio-economic development of the locality. However, to ensure the overall progress, the construction units, local authorities and functional agencies continue to coordinate closely, especially in mobilizing people to hand over the site and disbursing capital on schedule./.
Le Duc
Source: https://baolongan.vn/day-nhanh-tien-do-du-an-duong-tinh-822b-ket-noi-vung-bien-tao-da-phat-trien-a199087.html
Comment (0)